What This Guide Covers
A single-elevator LoRa deployment is the simplest entry point for multi-floor AGV operations. This guide is written for system integrators and field engineers, and explains how to commission the REEMAN AGV elevator control module from initial site survey through production handover. The focus is on practical checks that prevent rework, a repeatable commissioning sequence, and verification methods that keep the elevator's original safety systems intact.
This guide assumes the following scenario: one elevator serving two floors, one REEMAN autonomous forklift with a built-in LoRa radio, and a control module wired in parallel with (rather than replacing) the elevator's existing controller.
Pre-Power Checks: What to Verify Before First Power-On
Skipping the pre-power check is the most common cause of commissioning delays. Before powering the module, confirm the following four items.
LoRa Antenna Placement and Signal Coverage
The LoRa module communicates between the robot's waiting point and the elevator control cabinet. When mounting antennas, position them so that both areas have line of sight or minimal obstruction.
- Waiting point: the marked position where the robot stops to call the elevator. Verify that the robot maintains a stable LoRa link while stationary here.
- Inside the car: the robot must retain signal after entering, because the floor selection command is sent after entry.
If the elevator shaft is metal-lined or the machine room is far from the landing, plan for an external antenna extension cable or a higher-gain antenna. REEMAN has not published a specific dBm threshold for this module; in practice, integrators should field-test with the actual robot and module, and reposition the antenna if the link drops during movement.
Elevator Controller Interface Compatibility
Before wiring, gather the following information from the elevator maintenance manual or the elevator service provider:
| Item | Importance |
|---|---|
| Controller model and manufacturer | Determines whether the module's parallel wiring scheme matches the button/signal voltage levels |
| Button signal wiring (call, floor selection, open/close) | The module taps into these lines in parallel; voltage and polarity must match |
| Whether a door status signal is available | The robot needs this to judge when it can safely enter and exit |
| Floor position signal | Required for the module to report the current floor to the robot |
| Doorway clear width and car dimensions | Confirm the robot and its load can physically fit |
| Entry/exit path and turning radius | Verify the robot can align and maneuver at each landing |
| Elevator load capacity | Must exceed the combined weight of the robot plus maximum payload |
If the controller uses a proprietary serial protocol rather than dry-contact or voltage-level signals, a standard parallel module may not interface directly. In that case, contact REEMAN with the controller model to discuss an adaptation.
Safety-Preservation Review
The REEMAN module is designed to operate in parallel with the elevator's existing controls. This means:
- Manual call buttons remain fully functional.
- The elevator's built-in door protection circuits (safety edges, light curtains) are not bypassed.
- The original emergency stop chain remains intact.
Before installation, photograph the existing control panel and note which cables correspond to the call buttons, floor selector, open/close, and safety interlocks. This baseline helps with verification and later troubleshooting.
Step-by-Step Commissioning Sequence
The following sequence is a general framework based on a typical single-elevator LoRa deployment. Specific menu paths and pairing codes depend on the module firmware version; for screen-level details, refer to the latest REEMAN integration manual.
Step 1: Calibrate the Waiting Point
The waiting point is the robot's designated station outside the elevator landing. It must:
- Be far enough from the door that the robot does not obstruct passage while waiting
- Be on a flat surface where the robot can stop precisely and align its forks
- Be within reliable LoRa range of the module's antenna
Use the robot's built-in mapping tool or fleet software to record this location as a named waypoint. Test whether the robot can repeatedly navigate to this point from multiple approach directions.
Step 2: Pair the LoRa Module
Power on the elevator control module and place the robot at the waiting point. Initiate pairing from the robot's interface or the fleet management terminal. The module and robot should exchange IDs and confirm channel assignment.
After pairing, verify:
- The robot recognizes this module as the designated elevator for this floor
- The module reports elevator status (current floor, door status) to the robot
- No other LoRa devices on site are interfering with this channel
Step 3: Test Call and Response Latency
Trigger a call from the robot and measure how long the elevator takes to arrive at the landing. Repeat this test at least ten times, including:
- Calling from the lower floor to the upper floor
- Calling from the upper floor to the lower floor
- Calling when the elevator is already at the requested floor
- Calling when the elevator is on the opposite floor
Record the range of response times. Although REEMAN has not published a guaranteed maximum latency for this module, integrators should establish their own baseline during commissioning. If calls occasionally time out, first check LoRa signal strength and antenna position before proceeding.
Step 4: Confirm Door Status Feedback
The robot must receive an accurate door status signal before attempting to enter or exit. Test the following scenarios:
| Scenario | Expected feedback |
|---|---|
| Door fully closed | Module reports "closed" to the robot |
| Door fully open | Module reports "open" to the robot |
| Door in motion | Module reports "in motion" or holds the last stable state |
| Safety edge triggered while door is open | Module continues to report "open" (door does not close) |
| Safety edge triggered while door is closing | Module reports "in motion" or reverts to "open" |
Never allow the robot to enter when the door status signal is ambiguous. If the elevator controller does not provide a discrete door-open signal, discuss alternative detection options with REEMAN support (for example, an external door sensor on the module).
Verifying the Safety Chain and Emergency Stop Behavior
This is the most critical commissioning phase. The module must not change how the elevator responds to safety events.
Parallel-Verification Test
With the module powered on and the robot idle, perform the following tests manually:
- Press each floor's manual call button. The elevator must respond normally.
- Trigger the door safety edge while the door is closing. The door must reopen.
- Press the elevator emergency stop button. The car must stop and remain stopped until the emergency stop is reset.
- Reset the emergency stop. Normal operation must resume without restarting the module.
If any of the above behaviors change after installing the module, disconnect the module's power and check the wiring. The module should only tap into existing circuits and must not be inserted into the safety chain.
AGV Interaction Safety Test
With a trained operator present, have the robot complete a full cycle while monitoring the elevator's independent safety responses:
- Block the doorway with a test object as the robot enters. The elevator safety edge should stop the door; the robot should receive the door status change and stop.
- Press the emergency stop button while the robot is inside the car. The elevator must stop; the robot must detect the abnormal state and abort the task.
- Verify that the elevator can still be operated manually via its original buttons even while the module is active.
Record the results of each test. These records are part of the site acceptance package.
Production Workflow: From Waiting Point to Resumed Delivery
After commissioning, the robot operates according to the following verified workflow:
- Arrive at waiting point — The robot navigates to the calibrated waypoint and aligns.
- Call the elevator — A LoRa command is sent; the robot waits for arrival confirmation.
- Enter with load — Confirm door status is "open"; the robot enters the car and adjusts position to remain stable.
- Select target floor — A second LoRa command is sent from inside the car.
- Exit — On arrival, confirm door status is "open"; the robot exits and clears the doorway.
- Resume delivery — The robot proceeds to the next waypoint on the target floor.
This workflow has been in production at a REEMAN customer site in Dongguan, China, where an Ironhide autonomous forklift moves pallets of approximately 500 kg between two factory floors. The one-way route is about 200 meters, the narrowest aisle is about 2 meters, and the elevator dimensions are 2.4 × 1.8 × 2.6 meters. Deployment took about 5 days, and the system is estimated to run 80 full round-trip cycles per day. The original case document describes it as a machinery manufacturing plant.
For more on how AGV elevator integration fits into a broader automation architecture, see the AGV Technology Solutions guide on the REEMAN website.
Custom Integration and Fleet Expansion
The single-elevator LoRa solution described here is designed to operate without relying on the building's IT network. For facilities with multiple elevators or those requiring centralized fleet monitoring, REEMAN also supports MQTT-based communication, which can be routed through existing on-site network infrastructure.
REEMAN provides an open API, an SDK development kit, and sample code to support third-party system integration and secondary development of higher-level robot applications. Integrators building custom warehouse management system (WMS) connectors or fleet orchestration layers can use these resources to extend the elevator module's behavior beyond standard workflows.
Commissioning Checklist Summary
- LoRa antenna positioned to cover the waiting point and the car interior
- Elevator controller model and signal types recorded
- Door status and floor position signals confirmed available
- Physical fit verified: doorway width, car dimensions, load capacity
- Waiting point calibrated and repeatability tested
- Module paired with the robot; channel isolation confirmed
- Call/response latency baseline established for each floor combination
- Door status feedback accurate across all open/close/safety scenarios
- Original manual controls and safety chain verified unaffected
- Emergency stop behavior tested with the robot inside the car
- Full workflow executed successfully under supervision
FAQ
Can this module work with any brand of elevator?
The module connects to standard button and signal circuits via parallel wiring. It is compatible with many controllers that provide dry contacts or discrete voltage levels. Controllers using proprietary serial protocols may require an adapter. Provide the controller model to REEMAN before ordering to confirm compatibility.
Does the robot need Wi-Fi inside the elevator shaft?
No. A single-elevator deployment uses LoRa radio communication between the robot and the module. The robot does not need a Wi-Fi or Ethernet connection for elevator control inside the shaft or car. Network connectivity for fleet management is handled separately by the robot's own system.
What happens if the LoRa link is lost mid-cycle?
If the robot loses communication with the module while waiting, entering, or inside the car, its default behavior is to stop and retry the command. If the link does not recover within the configured timeout, the robot aborts the elevator task and alerts the fleet operator. The elevator itself continues to operate normally through its original controls.
Is the module certified to any safety standard?
The module preserves the elevator's existing safety chain but is itself an add-on device. For the overall AGV system, ISO 3691-4:2023 specifies safety requirements for driverless industrial trucks and their systems. In the United States, ANSI/ITSDF B56.5-2019 has been incorporated by reference by OSHA into its powered industrial truck standard. Integrators should ensure the fully installed system complies with applicable local regulations.
How long does commissioning usually take?
Commissioning time depends on site readiness, elevator accessibility, and the integrator's familiarity with the module. The deployment at the Dongguan machinery factory, including full workflow validation, took approximately 5 days. Integrators performing their first integration should allow extra time for antenna positioning trials and safety testing.
Source
- ISO, 2023 — ISO 3691-4:2023 Safety requirements for driverless industrial trucks
- Federal Register, 2022 — ANSI/ITSDF B56.5-2019 incorporated by reference
Ready to integrate multi-floor automation? Check the Ironhide autonomous forklift specifications, or contact our applications team to discuss your site layout and elevator configuration.